Ruwais 4th NGL Train Instrumentation Works

Scope of Work

Complete instrumentation works including works in greenfield testing and pre-commissioning:

Installation of cable trays – 75 km.

Below ground and above ground cabling – 2,500 km.

Cable glanding and termination – 41,000 glands.

Installation of junction boxes and marshalling/system cabinets.

Calibration, installation, and pre-commissioning works for field instruments – 6,500 instruments.

Assistance during commissioning and performance testing.